However, when observing the cursor placement
in a fully surfaced point cloud image, it becomes
evident whether the point cloud has low data
quality and if cursors have been accurately posi-
tioned on the data. Reviewing both metrics in the
point cloud can help increase accuracy and preci-
sion of the collected measurement data.
In the example in Figure 7, the technician was
not trained in how to validate the measurement
data in a stereo image, nor were they trained to
review the point cloud data and the cursor place-
ment upon the data. This led to providing a blade
tip-to-shroud clearance data of 0.031 in. (0.787 mm).
When a measurement system’s point cloud is
reviewed and pivoted in X, Y, and Z onscreen, it
immediately becomes obvious that a common
measurement error has been made. Note in
Figure 8 that when viewing the 3D data in the point
cloud image, the cursor labeled 3 of the measure-
ment’s reference plane (the lower, far-right magenta
cursor) was placed on data from the tip of the
blade, not on reference plane data for the shroud.
Note that the reference plane’s blue lines are
an extension of the three cursors used to establish
the reference plane. When that plane is tilted away
from the actual surface of the shroud, the tip-to-
shroud gap measurement appears smaller than it
actually is. Because the data quality in the point
cloud is extremely high, this presented an accurate
measurement. Because cursor 3 of the reference
plane was inaccurately placed on the tip of the
blade, and not on the shroud, the results obtained
are also wrong. This exemplifies a scenario where
good measurement image data quality resulted in
an accurate measurement but also produced incor-
rect measurement data.
To correct this error, the reference plane cursor
labeled 3 has been moved in the point cloud in
Figure 9 and placed on the shroud, which yields a
different result of 0.062 in. (1.57 mm). This 0.031 in.
(0.787 mm) discrepancy may seem small, but using
this incorrect measurement data can cost the asset
owner hundreds of thousands of dollars if the
equipment is taken out of service prematurely for
unneeded repairs. Also, leaving erroneous mea-
surement data unaddressed while the asset remains
in service can lead to efficiency losses in the power
turbine, impacting proper operations and resulting
in revenue losses.
The RVI image used in the second example is in
the compressor section of a large frame gas turbine
used to turn a massive electricity generator at a
power plant. In this type of industrial gas turbine
operation, downtime can bring losses of millions of
dollars a day and may also result in penalties and
fines, sometimes as much as US$1 million [4].
This power plant was in a planned outage.
An RVI task was scheduled to evaluate if the sta-
tionary vanes in the compressor section were
properly fixed in place or if they were becoming
loose and beginning to tilt, or “rock.” Some stator
rock is allowed, though significant damage and
MTD =0.855"
Tip of blade
1
3 4
2
+0.031"
IIV+
BLK
Figure 8. Power
turbine blade tip-to-
shroud, measured
with stereo.
Measurement data
found to be in error
by reviewing the
point cloud.
IIV+
BLK MTD =0.787"
Tip of blade
1 3
4
2
+0.062"
Figure 9. Power
turbine blade tip-to-
shroud, measured
with stereo.
Measurement data
error corrected by
correctly placing
the reference
plane’s cursors on
the shroud while
reviewing the point
cloud.
Blade tip trailing edge
Near-side stator floor
Far-side stator floor
Shroud/air seal
1
2
0.066"
MTD =0.405" 044
BLK
Figure 10. White
light image of
compressor section
with stator section
to be measured for
rocking.
FEATURE
|
REMOTEVT
46
M A T E R I A L S E V A L U A T I O N J U L Y 2 0 2 4
CREDIT:
WAYGATE
TECHNOLOGIES
CREDIT:
WAYGATE
TECHNOLOGIES
CREDIT:
WAYGATE
TECHNOLOGIES
unplanned forced outages can result when limits
are exceeded.
As previously discussed, to increase accuracy
and precision of RVI measurement data, the XYZ
point cloud data must exactly replicate the data
points on the surface being observed. Proper place-
ment of the cursors is critical.
In Figure 10 we see one measurement cursor,
labeled 1, on the shroud on the left, and the second
cursor, labeled 2, on the shoulder of the far-side
stator yielding measurement data of 0.066 in.
(1.676 mm).
In Figure 11, notice that the geometry of the
point cloud exactly matches the surface geometry as
observed in Figure 10. The data integrity of the point
cloud would allow for accurate measurements.
Also note the placement of the cursors in the point
cloud. The RVI task requires measuring the offset of
the stator floors, not the offset of the stator floors to
the shroud.
Even if shroud-to-stator were the required
measurement, the measurement in Figure 11 is
not taken perpendicular to the shroud’s shoulder,
nor is it entirely on the stator floor. It would be
close to impossible to measure perpendicularly
from the stator floor to the next stator floor using a
two-cursor length measurement.
In addition, the data was not validated in the
point cloud prior to providing the operator with the
results. Repairs were being discussed prematurely,
which could have resulted in additional outage
days and the loss of millions of dollars per day in
revenue, along with reduced availability of electric-
ity for the grid.
Once more, this illustrates a situation where the
measurement data is perfectly accurate but also
yields incorrect measurement results.
To resolve the measurement data errors, the
technical guidance for making this stator rock mea-
surement with RVI was reviewed. The best mea-
surement type to use would again be the depth
measurement. This measurement type measures
the perpendicular distance to or from the reference
plane. The reference plane would be placed on one
of the stator floors, and the fourth measurement
cursor would be placed on the other stator floor.
In Figure 12, a three-cursor depth reference
plane (depicted as a dotted-line triangle and labeled
1, 2, and 3) was placed on top of the far-side stator
floor, and the fourth measurement cursor, labeled 4,
was placed on top of the near-side stator floor. This
is seen in the white light image on the left half of
the image.
The resulting measurement data was 0.029 in.
(0.736 mm), a difference of 0.037 in. (0.939 mm)
from the original measurement data provided to the
plant manager. Having the correct data allowed the
plant to come back online without extending the
outage, while also saving millions of dollars.
A magnified view of the point cloud image
depicted in Figure 13 enables validation of the
Top of near-side stator floor
Top of far-side stator floor
Shroud
044
BLK MTD =0.405"
0.066"
Figure 11. White
light image of
compressor section
with incorrect
measurement
type and cursor
placement.
Blade tip trailing edge
Near-side stator floor
Far-side stator floor
Shroud/air seal
1
2
3
4
A =0.066"
B =0.029"
044
BLK
MTD
A =0.405"
B =0.827"
Figure 12. On the
left side of the image
is the white light
image of compressor
section with depth
measurement. On
the right is the point
cloud image of depth
measurement.
044
BLK
MTD B =0.827"
–0.029" Measurement reference plane
cursors on far-side stator floor
Measurement cursor on
near-side stator floor
Figure 13. Full point
cloud image of area
being measured.
Point cloud data
depicts exactly
the geometry of
the surfaces being
measured.
J U L Y 2 0 2 4 M A T E R I A L S E V A L U A T I O N 47
CREDIT:
WAYGATE
TECHNOLOGIES
CREDIT:
WAYGATE
TECHNOLOGIES
CREDIT:
WAYGATE
TECHNOLOGIES
Previous Page Next Page